Long Range Plan 2003 - 2008

FUSS BUILDING AND GROUNDS COMMITTEE
SUMMARY OF REPORT IDENTIFYING MAJOR AND MINOR PROJECTS

Since the church is now over 40 years old the Board of Trustees recommended that a study be performed to identify future building and grounds maintenance and repair projects with estimated costs.

A working group was formed and based on a professional architects sample report the group performed a comprehensive evaluation and prepared a report to meet this requirement. The full report is available in the church office.

The approach taken and conclusions reached are as follows:

(1) Based on the sample architect report a list of 33 project categories (each with subcategories) was established to cover the Church and Water's House. This formed a systematic basis for reviewing past projects and identifying future needs.

(2) A review was made of the past 30-year history of B&G projects and costs and a breakdown prepared for each category

(3) It was decided to arrange projects into two groups: (a) those over $10000 are designated major, and (b) those under $10000-are designated minor

(4) Minor projects over the past 30 years (adjusted for inflation) have averaged $7000 per year.

(5) Major project costs varied widely with no outlay for most years and a large outlay when major expenses occur. Roof resurfacing for both the flat section and the dome were the largest items.

(6) A list of approximately 40 minor projects which will need to be accomplished in the next four to five years was generated.

$8000 per year is a reasonable estimate for minor projects over the next few years

(7) MAJOR PROJECTS AND FURTHER COMMENTS

(7a) Repair and coat entire apron around church.
This item was recently completed.
$31500 (FY 2003)

(7b) Overhang section of Flat roof church building:
It is rotted out and repair and recovering is needed
$30000 (FY2004)

(7c) Reflecting Pool and Sidewalk - Cost highly dependent on solution selected
The front wall of one of the pools is gradually tipping inwards. A committee should be formed to establish long range plans since replacement could be very costly. Consider various alternate solutions such as reducing the size of the pools or possibly eliminating them. The timing is difficult to predict. The wall was stable for several years but has tilted some in the last 2 or 3 years. The sidewalks are tilted and should be replaced when major pool renovations are performed.

(7d) Trellis Wall, solid wall extensions and patio area on south side of church
Cost highly dependent on solution selected. This was added after the church was built and paid for by an individual donation. The solid and trellis wall are experiencing serious erosion and damage. The long range planning committee has identified that potential church usage is such that more space is desired. The possibility of adding space on the south side of the building is a possible option. A committee should be formed to develop plans for future actions and consider approaches which do not involve replacement of existing walls and incorporate any long range expansion plans approved by the congregation.

(7e) Refurbish Water's House Heating System $15000 estimated (FY 2006)
A technique for updating old steam systems in which plastic tubes are installed inside pipes and system converted to hot water has been identified as a cost effective upgrade

(7e) Replace Great Hall Carpeting $40000 estimated (FY2009)
Patching has been performed to date eventual replacement may be needed

(7f) Retile floors in dining rooms and hall $15090 estimated (FY2008)
Floors are slowly deteriorating-eventual replacement will be needed

(7g) Roof drainage system
Degradation of the drain field will require replacement

$15000 estimated (FY2007)

(7h) Main section of flat roof of church building $57500 (FY 2010??)
It is 25 years old but has been inspected and is still flexible. Annual inspection is recommended. Complete replacement is not anticipated for several years.

Excluding Items (7c) and (7d) total expenditures over the next 7 years including item (7a) are expected to total about $200000

Since Items (7c) and (7d) can total several hundred thousand dollars depending on actions that are selected it is recommended a committee be formed to identify options and develop cost
estimates.